On December 21st 2010, the assignment to start the contract activities for the procurement of the JT - 60SA Quench Protection Circuits (QPC) was entrusted to the company Nidec ASI S.p.A. formerly Ansaldo Sistemi Industriali S.p.A. by Consorzio RFX, who acts on behalf of the Italian National Research Council (CNR), the Voluntary Contributor Designated Institution , responsible for the "in - kind procurement" of this component. The QPC First Design Report, first deliverable of the JT - 60SA QPC procurement, was approved on 21 July 2011 (M ilestone M S1) . The Report on the Factory Type Test of First TFC and PFC QPC Units , second deliverable of the JT - 60SA QPC procurement, was approved on 21 January 2013 (MS2) . The report on Ground Transportation Method (MS6) , third deliverable, was approved on 14 th May 2013 and the delivery of the system on Site was completed between September and December 2014 ( MS4 ). The report on TFC&PFC QPC Factory Routine Tests, fourth deliverable of the QPC procurement, was approved on 13 th Augu st 2014 (MS 3 ) . The report on " TFC&PFC QPCs Final Acceptance Tests on Site ", fifth deliverable of the QPC procurement , was approved on 10 th July 2015 (MS5) . The document hereinafter attached is the AoC Final Report - Acceptance Data Package , composed of the following main parts (the links to the relevant documents are listed) : - Final version of PA, Annex A and Annex B and amendments - Final version of AoC and amendments - Final Technical Specification for the Supplier - Consorzio RFX quality plan (last revision) - Procurement plan (last revision) - Risk management plan (last revision) - Control Plan (last revision) - Project and documentation schedule (last revision) - Ground transportation method and records of inspections - AoC progress reports - List of approved change requests - Supplier Final Report o Final design report o Factory type test procedures and reports o Factory routine test procedures and reports o Specific certifications o Site test procedures and reports o Transportation documents o Installation, commissioning and site te sts plans o Use and maintenance manual (including layout drawings, schematic diagrams and spare part list) o QPC system configuration management o QPC Component Traceability o Training report.

AOC FINAL REPORT FOR QPC PROCUREMENT - AGREEMENT OF COLLABORATION F4E - CNR FOR THE JOINT IMPLEMENTATION OF THE PROCUREMENT ARRANGEMENT FOR QUENCH PROTECTION CIRCUITS FOR POLOIDAL AND TOROIDAL COILS FOR THE SATELLITE TOKAMAK PROGRAMME

Gaio E
2015

Abstract

On December 21st 2010, the assignment to start the contract activities for the procurement of the JT - 60SA Quench Protection Circuits (QPC) was entrusted to the company Nidec ASI S.p.A. formerly Ansaldo Sistemi Industriali S.p.A. by Consorzio RFX, who acts on behalf of the Italian National Research Council (CNR), the Voluntary Contributor Designated Institution , responsible for the "in - kind procurement" of this component. The QPC First Design Report, first deliverable of the JT - 60SA QPC procurement, was approved on 21 July 2011 (M ilestone M S1) . The Report on the Factory Type Test of First TFC and PFC QPC Units , second deliverable of the JT - 60SA QPC procurement, was approved on 21 January 2013 (MS2) . The report on Ground Transportation Method (MS6) , third deliverable, was approved on 14 th May 2013 and the delivery of the system on Site was completed between September and December 2014 ( MS4 ). The report on TFC&PFC QPC Factory Routine Tests, fourth deliverable of the QPC procurement, was approved on 13 th Augu st 2014 (MS 3 ) . The report on " TFC&PFC QPCs Final Acceptance Tests on Site ", fifth deliverable of the QPC procurement , was approved on 10 th July 2015 (MS5) . The document hereinafter attached is the AoC Final Report - Acceptance Data Package , composed of the following main parts (the links to the relevant documents are listed) : - Final version of PA, Annex A and Annex B and amendments - Final version of AoC and amendments - Final Technical Specification for the Supplier - Consorzio RFX quality plan (last revision) - Procurement plan (last revision) - Risk management plan (last revision) - Control Plan (last revision) - Project and documentation schedule (last revision) - Ground transportation method and records of inspections - AoC progress reports - List of approved change requests - Supplier Final Report o Final design report o Factory type test procedures and reports o Factory routine test procedures and reports o Specific certifications o Site test procedures and reports o Transportation documents o Installation, commissioning and site te sts plans o Use and maintenance manual (including layout drawings, schematic diagrams and spare part list) o QPC system configuration management o QPC Component Traceability o Training report.
2015
Istituto gas ionizzati - IGI - Sede Padova
Rapporto finale di progetto
-
File in questo prodotto:
Non ci sono file associati a questo prodotto.

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/20.500.14243/290276
Citazioni
  • ???jsp.display-item.citation.pmc??? ND
  • Scopus ND
  • ???jsp.display-item.citation.isi??? ND
social impact