The main activities, developed from 24th to 30th month relative to the FLEXICAST project, have focused on the following steps: oMeetings with involved partners oFilling out of the data sheets oData analysis The meetings among the involved partners have been necessary to identify the useful data to collect in order to conduct a LCA analysis. The data obtained and those we will acquire in subsequent meetings will be elaborated and implemented within the GaBi software.

FLEXICAST 30 months WP7 report

Antonino Bonanno;Giuseppe Rizzo
2015

Abstract

The main activities, developed from 24th to 30th month relative to the FLEXICAST project, have focused on the following steps: oMeetings with involved partners oFilling out of the data sheets oData analysis The meetings among the involved partners have been necessary to identify the useful data to collect in order to conduct a LCA analysis. The data obtained and those we will acquire in subsequent meetings will be elaborated and implemented within the GaBi software.
2015
Istituto per le Macchine Agricole e Movimento Terra - IMAMOTER - Sede Ferrara
Rapporto intermedio di progetto
LCA
Foundry
Cast Iron
File in questo prodotto:
Non ci sono file associati a questo prodotto.

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/20.500.14243/304375
Citazioni
  • ???jsp.display-item.citation.pmc??? ND
  • Scopus ND
  • ???jsp.display-item.citation.isi??? ND
social impact