This document contains a draft of the SPIDER commissioning and power test plan. After a description of the installation and commissioning sequence at the basis of the Baseline used for the SPIDER on site activities, it describes in detail an updated proposal of overall sequence of integrated commissioning to be performed with the Beams Source and described for the first time in the deliverable WP2013 - T5.1/P1. Before the start of the integrated commissioning detailed planning of each stage will be performed.

Draft commissioning procedure and sequence of SPIDER beam source

Serianni G;Toigo V
2015

Abstract

This document contains a draft of the SPIDER commissioning and power test plan. After a description of the installation and commissioning sequence at the basis of the Baseline used for the SPIDER on site activities, it describes in detail an updated proposal of overall sequence of integrated commissioning to be performed with the Beams Source and described for the first time in the deliverable WP2013 - T5.1/P1. Before the start of the integrated commissioning detailed planning of each stage will be performed.
2015
Istituto gas ionizzati - IGI - Sede Padova
Rapporto finale di progetto
Neutral Beam Test Facility
NBTF
SPIDER Beam Source
File in questo prodotto:
Non ci sono file associati a questo prodotto.

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/20.500.14243/308119
Citazioni
  • ???jsp.display-item.citation.pmc??? ND
  • Scopus ND
  • ???jsp.display-item.citation.isi??? ND
social impact