This report gives an overview of the work done on Task 6.2 during 2015, concerning Schedule Baseline and Coordination Meetings, held during Installation Phase of SPIDER project at RFX PRIMA Site.

SPIDER Schedule Baseline and list of weekly Site Progress Coordination Meetings (SPCM)

Sottocornola A
2016

Abstract

This report gives an overview of the work done on Task 6.2 during 2015, concerning Schedule Baseline and Coordination Meetings, held during Installation Phase of SPIDER project at RFX PRIMA Site.
2016
Istituto gas ionizzati - IGI - Sede Padova
Rapporto intermedio di progetto
Neutral Beam Test Fcility
NBTF
SPIDER
PRIMA
File in questo prodotto:
Non ci sono file associati a questo prodotto.

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/20.500.14243/315904
Citazioni
  • ???jsp.display-item.citation.pmc??? ND
  • Scopus ND
  • ???jsp.display-item.citation.isi??? ND
social impact