The document defines the insulation test to be executed on the SPIDER CODAS I&C cubicles and cable trays that are installed in SPIDER HVD - high voltage area and are not at the potential of the HVD itself. These are four I&C cubicles that are mounted on an insulation pedestal and are electrically connected with two cable trays that hang from the ceiling through insulated hooks. The test results are also reported.

Insulation test on the SPIDER CODAS I&C cubicles and cable trays located in the HVD high-voltage area

Luchetta A;Zampiva E
2016

Abstract

The document defines the insulation test to be executed on the SPIDER CODAS I&C cubicles and cable trays that are installed in SPIDER HVD - high voltage area and are not at the potential of the HVD itself. These are four I&C cubicles that are mounted on an insulation pedestal and are electrically connected with two cable trays that hang from the ceiling through insulated hooks. The test results are also reported.
2016
Istituto gas ionizzati - IGI - Sede Padova
Rapporto finale di progetto
Neutral Beam Test Facility
NBTF control
interlock and safety
SPIDER CODAS Infrastructure
HVD high-voltage area
File in questo prodotto:
Non ci sono file associati a questo prodotto.

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/20.500.14243/318143
Citazioni
  • ???jsp.display-item.citation.pmc??? ND
  • Scopus ND
  • ???jsp.display-item.citation.isi??? ND
social impact