This progress report of activities covers the period from 01-01-2019 to 31-03-2019. In Q6 all diagnostics, except MITICA optical thermal sensors, entered the procurement phase, while some of them are also progressing in installation & integration (Neutrons, STRIKE, Tomography).

Framework Contract F4E-OFC-531 Specific Contract F4E-OFC-531-02 Quarter 6: Activity Progress Report

Pasqualotto R;Sottocornola A
2019

Abstract

This progress report of activities covers the period from 01-01-2019 to 31-03-2019. In Q6 all diagnostics, except MITICA optical thermal sensors, entered the procurement phase, while some of them are also progressing in installation & integration (Neutrons, STRIKE, Tomography).
2019
Istituto gas ionizzati - IGI - Sede Padova
Rapporto finale di progetto
Neutral Beam Test Facility
NBTF
F4E-OFC
PRIMA
File in questo prodotto:
Non ci sono file associati a questo prodotto.

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/20.500.14243/411016
Citazioni
  • ???jsp.display-item.citation.pmc??? ND
  • Scopus ND
  • ???jsp.display-item.citation.isi??? ND
social impact