This progress report of activities covers the period from 01-01-2020 to 31-03-2020. In Q10 all diagnostics completed their order procedures, i.e. all orders for supplies have been placed, except for MITICA optical thermal sensors, which is nearly finished, as a supplier has been selected and the order is under preparation.
Framework Contract F4E-OFC-531 Specific Contract F4E-OFC-531-02 Quarter 10: Activity Progress Report
Pasqualotto R;Sottocornola A
2020
Abstract
This progress report of activities covers the period from 01-01-2020 to 31-03-2020. In Q10 all diagnostics completed their order procedures, i.e. all orders for supplies have been placed, except for MITICA optical thermal sensors, which is nearly finished, as a supplier has been selected and the order is under preparation.File in questo prodotto:
Non ci sono file associati a questo prodotto.