This paper proposes a tabu search heuristic for the Quay Crane Scheduling Problem (QCSP), the problem of scheduling a fixed number of quay cranes in order to load and unload containers into and from a ship. The optimality criterion considered is the minimum completion time. Precedence and non-simultaneity constraints between tasks are taken into account. The former originate from the different kind of operations that each crane has to perform; the latter are needed in order to avoid interferences between the cranes. The QCSP is decomposed into a routing problem and a scheduling problem. The routing problem is solved by a tabu search heuristic, while a local search technique is used to generate the solution of the scheduling problem. This is done by minimizing the longest path length in a disjunctive graph. The effectiveness of our algorithm is assessed by comparing it to a branch-and-cut algorithm and to a Greedy Randomized Adaptive Search Procedure (GRASP).

A tabu search heuristic for the quay crane scheduling problem

Marcello Sammarra;
2007

Abstract

This paper proposes a tabu search heuristic for the Quay Crane Scheduling Problem (QCSP), the problem of scheduling a fixed number of quay cranes in order to load and unload containers into and from a ship. The optimality criterion considered is the minimum completion time. Precedence and non-simultaneity constraints between tasks are taken into account. The former originate from the different kind of operations that each crane has to perform; the latter are needed in order to avoid interferences between the cranes. The QCSP is decomposed into a routing problem and a scheduling problem. The routing problem is solved by a tabu search heuristic, while a local search technique is used to generate the solution of the scheduling problem. This is done by minimizing the longest path length in a disjunctive graph. The effectiveness of our algorithm is assessed by comparing it to a branch-and-cut algorithm and to a Greedy Randomized Adaptive Search Procedure (GRASP).
2007
container terminal
crane scheduling
disjunctive graph
Tabu search
File in questo prodotto:
Non ci sono file associati a questo prodotto.

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/20.500.14243/153214
Citazioni
  • ???jsp.display-item.citation.pmc??? ND
  • Scopus 170
  • ???jsp.display-item.citation.isi??? 130
social impact