Due to the increasing competitiveness of businesses, project planning and scheduling have become a challenging theme in the last years. In this paper, we propose a two-stage stochastic programming model for the resource constrained project scheduling problem, taking into account the stochasticity of activity durations. In this formulation, assuming that some activity duration scenarios are known, resource allocations are taken in the first stage, while scheduling decisions are postponed in the second stage. The resulting problem is a mixed integer problem with recourse, where binary variables appear in the first stage. In order to efficiently solve the problem, a decomposition algorithm is developed, based on the well-known integer L-shaped method. Detailed computational results are presented for a set of benchmark instances taken from the literature.

A two-stage stochastic programming model for the resource constrained project scheduling problem under uncertainty

Di Puglia Pugliese Luigi;
2018

Abstract

Due to the increasing competitiveness of businesses, project planning and scheduling have become a challenging theme in the last years. In this paper, we propose a two-stage stochastic programming model for the resource constrained project scheduling problem, taking into account the stochasticity of activity durations. In this formulation, assuming that some activity duration scenarios are known, resource allocations are taken in the first stage, while scheduling decisions are postponed in the second stage. The resulting problem is a mixed integer problem with recourse, where binary variables appear in the first stage. In order to efficiently solve the problem, a decomposition algorithm is developed, based on the well-known integer L-shaped method. Detailed computational results are presented for a set of benchmark instances taken from the literature.
2018
Istituto di Calcolo e Reti ad Alte Prestazioni - ICAR
Inglese
ICORES2019
2018-January
194
200
9789897582851
http://www.scopus.com/record/display.url?eid=2-s2.0-85047965777&origin=inward
Sì, ma tipo non specificato
19/02/2019, 21/02/2019
Praga
Integer L-shaped
RCPSP
Stochastic Programming
Uncertainty
4
none
Bruni Maria, Elena; DI PUGLIA PUGLIESE, Luigi; Beraldi, Patrizia; Guerriero, Francesca
273
info:eu-repo/semantics/conferenceObject
04 Contributo in convegno::04.01 Contributo in Atti di convegno
File in questo prodotto:
Non ci sono file associati a questo prodotto.

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/20.500.14243/385454
Citazioni
  • ???jsp.display-item.citation.pmc??? ND
  • Scopus 10
  • ???jsp.display-item.citation.isi??? ND
social impact