To reach fusion conditions and control the plasma configuration in ITER, the next step in tokamak fusionresearch, two neutral beam injectors (NBIs) will supply 16.5 MW each, by neutralizing accelerated negativehydrogen or deuterium ions. The requirements of ITER NBIs (40A/1 MeV D- ions for <=1 h, 46A/870 keV H- ionsfor <=1000 s) have never been simultaneously attained. So in the Neutral Beam Test Facility (NBTF, ConsorzioRFX, Italy) the operation of the full-scale ITER NBI prototype (MITICA) will be tested and optimised up to fullperformances, focussing on accelerator (including voltage holding), beam optics, neutralisation, residual ionremoval. The NBTF includes also the full-scale prototype of the ITER NBI source with 100 keV particle energy(SPIDER), for early investigation of: negative ion production and extraction, source uniformity, negative ioncurrent density and beam optics.This paper will describe the main results of the first two years of SPIDER operation, devoted to characterizingplasma and beam parameters, including investigation of RF-plasma coupling efficiency and magnetic filter fieldeffectiveness in reducing co-extracted electrons. SPIDER is progressing towards the first caesium injection, whichaims at increasing the negative ion density. A major shutdown, planned for 2021, to solve the issues identifiedduring the operation and to carry out programmed modifications, will be outlined.The installation of each MITICA power supply and auxiliary system is completed; in-vessel mechanicalcomponents are under procurement by Fusion for Energy (F4E). Integration, commissioning and test of the powersupplies, procured by F4E and QST, as the Japanese Domestic Agency (JADA), will be presented. In particular,1.0MV insulating tests were carried out step-by-step and successfully completed. In 2020 integrated tests of thepower supplies on the accelerator dummy load started, including the assessment of their resilience to acceleratorgrid breakdowns using a short-circuit device located in vacuum.The aggressive programme, to validate the NBI design at NBTF and to meet ITER schedule (requiring NBIs inoperation in 2032), will be outlined. Unfortunately, in 2020 the coronavirus disease infection affected the NBTFactivities. A solution to proceed with integrated power tests despite the coronavirus is presented.

On the road to ITER NBIs: SPIDER improvement after first operation and MITICA construction progress

Toigo V
Primo
;
Serianni G
;
Grando L;Luchetta A;Pasqualotto R;Zaccaria P;Agostinetti P;Agostini M;Antoni V;Barbisan M;Brombin M;Dalla Palma M;De Lorenzi A;Fadone M;Gaio E;Manduchi G;Martines E;Martini S;Milazzo R;Pomaro N;Recchia M;Sottocornola A;Spagnolo S;Spolaore M;Taliercio C;Terranova D;Zaupa M;Zuin M;Muraro A;Rebai M;Tardocchi M;Giacomelli L;Rigamonti D;Taccogna F;Bruno D;Rutigliano M;
2021

Abstract

To reach fusion conditions and control the plasma configuration in ITER, the next step in tokamak fusionresearch, two neutral beam injectors (NBIs) will supply 16.5 MW each, by neutralizing accelerated negativehydrogen or deuterium ions. The requirements of ITER NBIs (40A/1 MeV D- ions for <=1 h, 46A/870 keV H- ionsfor <=1000 s) have never been simultaneously attained. So in the Neutral Beam Test Facility (NBTF, ConsorzioRFX, Italy) the operation of the full-scale ITER NBI prototype (MITICA) will be tested and optimised up to fullperformances, focussing on accelerator (including voltage holding), beam optics, neutralisation, residual ionremoval. The NBTF includes also the full-scale prototype of the ITER NBI source with 100 keV particle energy(SPIDER), for early investigation of: negative ion production and extraction, source uniformity, negative ioncurrent density and beam optics.This paper will describe the main results of the first two years of SPIDER operation, devoted to characterizingplasma and beam parameters, including investigation of RF-plasma coupling efficiency and magnetic filter fieldeffectiveness in reducing co-extracted electrons. SPIDER is progressing towards the first caesium injection, whichaims at increasing the negative ion density. A major shutdown, planned for 2021, to solve the issues identifiedduring the operation and to carry out programmed modifications, will be outlined.The installation of each MITICA power supply and auxiliary system is completed; in-vessel mechanicalcomponents are under procurement by Fusion for Energy (F4E). Integration, commissioning and test of the powersupplies, procured by F4E and QST, as the Japanese Domestic Agency (JADA), will be presented. In particular,1.0MV insulating tests were carried out step-by-step and successfully completed. In 2020 integrated tests of thepower supplies on the accelerator dummy load started, including the assessment of their resilience to acceleratorgrid breakdowns using a short-circuit device located in vacuum.The aggressive programme, to validate the NBI design at NBTF and to meet ITER schedule (requiring NBIs inoperation in 2032), will be outlined. Unfortunately, in 2020 the coronavirus disease infection affected the NBTFactivities. A solution to proceed with integrated power tests despite the coronavirus is presented.
2021
Istituto per la Scienza e Tecnologia dei Plasmi - ISTP
Inglese
168
07-2021
112622-1
112622-10
10
https://www.sciencedirect.com/science/article/pii/S0920379621003987?casa_token=rriWjuGCiZ0AAAAA:NFBHxB7214H7sKy449bPM1eNElz60q8ZBrKgxFgJnzc5sATyVN90VbkwFjd3Sp2NoFozYLmGjw
Sì, ma tipo non specificato
ITER neutral beam injectors
Negative ion beam
Negative ion source
Electronic ISSN: 1873-7196 - https://www.scopus.com/inward/record.uri?eid=2-s2.0-85106932358&oi=10.1016/j.fusengdes.2021.112622&partnerID=40&md5=cdf987972447061888ee78564daad43c - The work leading to this publication has been funded partially by Fusion for Energy and part of this work has been carried out within the framework of the EUROfusion Consortium and has received funding from the Euratom research and training programme.
144
info:eu-repo/semantics/article
262
Toigo, V; Marcuzzi, D; Serianni, G; Boldrin, M; Chitarin, G; Dal Bello, S; Grando, L; Luchetta, A; Pasqualotto, R; Zaccaria, P; Zanotto, L; Agnello, R...espandi
01 Contributo su Rivista::01.01 Articolo in rivista
restricted
   Implementation of activities described in the Roadmap to Fusion during Horizon 2020 through a Joint programme of the members of the EUROfusion consortium
   EUROfusion
   H2020
   633053
File in questo prodotto:
File Dimensione Formato  
prod_454807-doc_175463.pdf

solo utenti autorizzati

Descrizione: On the road to ITER NBIs_ SPIDER improvement after first operation and MITICA construction progress
Tipologia: Versione Editoriale (PDF)
Licenza: NON PUBBLICO - Accesso privato/ristretto
Dimensione 9.12 MB
Formato Adobe PDF
9.12 MB Adobe PDF   Visualizza/Apri   Richiedi una copia

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/20.500.14243/399034
Citazioni
  • ???jsp.display-item.citation.pmc??? ND
  • Scopus 61
  • ???jsp.display-item.citation.isi??? 58
social impact