The Divertor Tokamak Test facility (DTT) is the new tokamak under construction in Frascati (Italy), with the main aim of testing different divertor magnetic configurations and technologies in view of DEMO. The Heating and Current Drive function will be provided also by one Neutral Beam Injector (NBI), accelerating negative Deuterium ions with an energy of 510 keV, giving an output power of 10 MW maximum. The Acceleration Grid Power Supply (AGPS), with 3 stages rated 167 kV each, will feed the NBI accelerator. For optical reasons, the insulating gap among the acceleration grids is at the limit of the voltage holding in vacuum, therefore frequent arc breakdowns (BD) among the grids will occur, requiring the quick switch-off of the AGPS to limit the arc energy. For the AGPS, beside the ITER-like scheme including gas-insulated HV components, an innovative approach based on the Modular Multilevel Converter (MMC) technology is being considered. This would include air-insulated HV converters, requiring a huge building volume, which at present is not available in close proximity to the tokamak building. The alternative of installing the MMC converters in a new building to be erected in an available area located far from the tokamak, and connecting the AGPS to the load with HV coaxial cables, is under study. This paper presents the studies carried out to verify the impact of the cables length on the arc energy, in case of breakdown among the grids, and to estimate the magnitude of the voltage oscillations due to resonance effects. These oscillations can occur not only between each hot pole and the return conductor, endangering the cable insulation, but also between the return conductor and local ground, with potential consequences on the laying method, the human safety and the electromagnetic compatibility with sensitive apparatus nearby, which have all been evaluated.

Studies on high voltage dc cable connection to supply the acceleration grids of the Neutral Beam Injector for DTT

Murari A;Granucci G;
2022

Abstract

The Divertor Tokamak Test facility (DTT) is the new tokamak under construction in Frascati (Italy), with the main aim of testing different divertor magnetic configurations and technologies in view of DEMO. The Heating and Current Drive function will be provided also by one Neutral Beam Injector (NBI), accelerating negative Deuterium ions with an energy of 510 keV, giving an output power of 10 MW maximum. The Acceleration Grid Power Supply (AGPS), with 3 stages rated 167 kV each, will feed the NBI accelerator. For optical reasons, the insulating gap among the acceleration grids is at the limit of the voltage holding in vacuum, therefore frequent arc breakdowns (BD) among the grids will occur, requiring the quick switch-off of the AGPS to limit the arc energy. For the AGPS, beside the ITER-like scheme including gas-insulated HV components, an innovative approach based on the Modular Multilevel Converter (MMC) technology is being considered. This would include air-insulated HV converters, requiring a huge building volume, which at present is not available in close proximity to the tokamak building. The alternative of installing the MMC converters in a new building to be erected in an available area located far from the tokamak, and connecting the AGPS to the load with HV coaxial cables, is under study. This paper presents the studies carried out to verify the impact of the cables length on the arc energy, in case of breakdown among the grids, and to estimate the magnitude of the voltage oscillations due to resonance effects. These oscillations can occur not only between each hot pole and the return conductor, endangering the cable insulation, but also between the return conductor and local ground, with potential consequences on the laying method, the human safety and the electromagnetic compatibility with sensitive apparatus nearby, which have all been evaluated.
2022
Istituto per la Scienza e Tecnologia dei Plasmi - ISTP
Inglese
187
113356-1
113356-6
6
https://www.sciencedirect.com/science/article/abs/pii/S0920379622003477
Sì, ma tipo non specificato
Neutral Beam Injector
Acceleration Grid Power Supply
Modular Multilevel Converter
DTT
Electronic ISSN: 1873-7196 - Available online 6 December 2022 - This work has been carried out within the framework of the EUROfusion Consortium, funded by the European Union via the Euratom Research and Training Programme (Grant Agreement No 101052200 - EUROfusion).
5
info:eu-repo/semantics/article
262
Santoro, F; Ferro, A; Murari, A; Granucci, G; Romano, R
01 Contributo su Rivista::01.01 Articolo in rivista
none
   Implementation of activities described in the Roadmap to Fusion during Horizon 2020 through a Joint programme of the members of the EUROfusion consortium
   EUROfusion
   H2020
   633053
File in questo prodotto:
Non ci sono file associati a questo prodotto.

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/20.500.14243/414637
Citazioni
  • ???jsp.display-item.citation.pmc??? ND
  • Scopus 1
  • ???jsp.display-item.citation.isi??? 1
social impact